Question
Download Solution PDFIf 36 persons can finish 50% of work in 12 days. In how many days 72 person can finish the complete work?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFConcept used:
(M1 × D1)/W1 = (M2 × D2)/W2
Where,
M1 = First man
D1 = First day
W1 = First work
M2 = Second man
D2 = Second day
W2 = Second work
Calculation:
According to the question:
M1 = 36
D1 = 12
W1 = 50% = 1/2
M2 = 72
D2 = x days
W2 = 50% = 1/2
M1 × D1 = M2 × D2
⇒ (36 × 12)/1/2 = (72 × x)
⇒ x = (36 × 24)/72 = 12 days
∴ The required answer will be 12 days.
Last updated on Jul 4, 2025
-> The CUET 2025 provisional answer key has been made public on June 17, 2025 on the official website.
-> The CUET 2025 Postponed for 15 Exam Cities Centres.
-> The CUET 2025 Exam Date was between May 13 to June 3, 2025.
-> 12th passed students can appear for the CUET UG exam to get admission to UG courses at various colleges and universities.
-> Prepare Using the Latest CUET UG Mock Test Series.
-> Candidates can check the CUET Previous Year Papers, which helps to understand the difficulty level of the exam and experience the same.