Question
Download Solution PDFWhich of the following is a power plant with high initial cost, low running and maintenance cost and with NO standby losses?
This question was previously asked in
MPPGCL JE Electrical 19 March 2019 Shift 2 Official Paper
Answer (Detailed Solution Below)
Option 3 : Hydro-electric power plant
Free Tests
View all Free tests >
MPPGCL JE Electrical Full Test 1
3.9 K Users
100 Questions
100 Marks
120 Mins
Detailed Solution
Download Solution PDFThe hydroelectric power plant has a high initial cost because of the construction of the dam.
Hence, the correct answer is option 3.
Comparison between different power plants:
Last updated on May 29, 2025
-> MPPGCL Junior Engineer result PDF has been released at the offiical website.
-> The MPPGCL Junior Engineer Exam Date has been announced.
-> The MPPGCL Junior Engineer Notification was released for 284 vacancies.
-> Candidates can apply online from 23rd December 2024 to 24th January 2025.
-> The selection process includes a Computer Based Test and Document Verification.
-> Candidates can check the MPPGCL JE Previous Year Papers which helps to understand the difficulty level of the exam.