Question
Download Solution PDFP can do a job in 8 days, Q in 12 days and R in 16 days. How many days are required to finish the work by R, if he is assisted by P and Q on every second day?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
P can do a job in 8 days, Q in 12 days and R in 16 days.
Concept:
If work is done completely in N days then,
the work done in 1 day will be \(\frac{1}{N}\)
Solution:
According to the question,
P can do a job in 8 days.
Work done by P in 1 day is \(\frac{1}{8}\)
Q can do a job in 12 days
Work done by Q in 1 day is \(\frac{1}{12}\)
R can do a job in 16 days
Work done by R in 1 day is \(\frac{1}{16}\)
Work done by P and Q together is \( \frac{1}{8}+\frac{1}{12}=\frac{15}{72}\)
Since every second day, P and Q are assisting R.
Work done by P, Q, and R together is \( \frac{15}{72}+\frac{1}{16}=\frac{13}{48}\)
Work done in two days will be,
the sum of work done by R in 1 day and work done by P, Q, and R together on the second day.
\( \frac{13}{48}+\frac{1}{16}=\frac{16}{48}\)
Time taken to complete the work,
\( \frac{48}{16}\times 2=6\)
Hence, option 4 is correct.
Last updated on May 26, 2025
-> The MAHA TAIT Admit Card 2025 has been released on its official website.
-> The MAHA TAIT 2025 will be conducted from 27th to 30th of May 2025 abd from 2nd to 5th of June 2025.
-> The minimum educational qualification required for the Maharashtra Teaching Aptitude Test is a graduation degree from a recognized university.
-> To practice and prepare well for the MAHA TAIT 2025, solve the MAHA TAIT Previous Years' Papers for free.